Unit handover decisions
Keep a demolition daily exception log that prompts decisions
- Unit handover decisions

A daily report can list progress without making unresolved decisions visible. An exception log focuses on the items preventing the next agreed step. It is useful when a commercial strip-out has several decision-makers and the same question keeps returning at each site meeting.
Write the exception as a question
Describe the exact location, observed condition and decision required. Replace vague entries such as services issue with a specific request to identify the owner of a labelled connection. Attach the relevant drawing or photograph rather than repeating an uncertain interpretation as fact.
Assign an answer, not just a recipient
Name the person responsible for obtaining the answer and the party qualified to make it. Record which work is paused and which work can continue under the existing plan. A copied email does not show that anyone has accepted responsibility for the decision.
Close with a traceable instruction
When the answer arrives, reference the document or instruction and update the affected scope. Keep the original question alongside the resolution. An item should not disappear because a meeting ended or because a different crew arrives tomorrow.
FAQ
Questions about this topic
- Is this a substitute for a change order?
- No. It records the question and resolution. Contract changes, design instructions and approvals still follow the project's agreed process.
Connect this decision to your project
Start with your situation, compare the related work photos and tell us which removal boundary needs review.
